QUESTION: Councillor C. Brady
To ask the Chief Executive for a progress update on flood alleviation measures at Esker Lane, Crugh Cross Finnstown and Hillcrest Walk, including works completed, works committed, works underway and anticipated timelines for remaining works, and, recognising the significant and often complex work undertaken by the Council to reduce flood risk at these locations, to outline the progress achieved to date in addressing concerns raised regarding flooding at these locations.
REPLY:
Esker Lane
The surface water drainage network lines have been jetted and surveyed in the area. Vegetation has been cut back along the drainage ditch on the St Edmundsbury side of the road, to provide access to cleaning out the drainage ditch. As part of these works a old culvert was discovered that was not on previous drainage network records. Jetting and cleaning of this culvert through which the ditch passes is currently ongoing, but will be completed within coming weeks.
Hillcrest Walk
Jetting and CCTV survey works have identified a number of defects within the surface water drainage network, including open joints and significant tree root ingress. A specialist contractor is currently carrying out root-cutting works to facilitate the completion of the CCTV survey and allow a full assessment of the network. Once completed, the extent of any remedial works required and timelines can be determined.
Finnstown Crugh Cross (Esker/ Newcastle Road)
Jetting and CCTV surveys have been carried out over a number of nights to investigate the cause of flooding issues along the Esker and Newcastle Road. Initial findings have identified multiple collapses within the drainage network which will require civil engineering works to rectify. The surveys have also identified what appears to be an old stone culvert crossing the junction, which is suspected to have collapsed. However, due to significant silt build-up and limited access, its condition can't be fully confirmed at this time.
A Civil Engineering contractor has been organised to carry out enabling works to facilitate survey access to buried manholes which will allow a full assessment of the culvert.
The CCTV survey has identified irregularities within the surface water network that were not previously recorded on our system, which has delayed the progress on site.
Once these investigations are complete, Natural Water will be in a position to develop a package of remedial works to address the identified defects and eliminate the risk of further flooding at these locations.