COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE

Wednesday, October 28, 2026

QUESTION NO.10

QUESTION: Councillor L. O'Toole

That the Chief Executive provide an update on the ongoing flood alleviation and drainage works taking place along Esker Road and Newcastle Road Lucan, including details of the works carried out to date, any outstanding issues and the expected completion dates. Can Management also confirm whether these works are expected to resolve the recurring flooding issues in both locations?

REPLY:

Jetting and CCTV surveys have been carried out over a number of nights to investigate the cause of flooding issues along the Esker and Newcastle Road. Initial findings have identified multiple collapses within the drainage network which will require civil engineering works to rectify. The surveys have also identified what appears to be an old stone culvert crossing the junction, which is suspected to have collapsed. However, due to significant silt build-up and limited access, its condition can't be fully confirmed at this time.

A Civil Engineering contractor has been organised to carry out enabling works to facilitate survey access to buried manholes which will allow a full assessment of the culvert.

The CCTV survey has identified irregularities within the surface water network that were not previously recorded on our system, which has delayed the progress on site.

Once these investigations are complete, Natural Water will be in a position to develop a package of remedial works to address the identified defects and eliminate the risk of further flooding at these locations.