QUESTION: Councillor L. O'Toole
That this Area Committee requests that members be provided with the full SYSTRA traffic modelling report relating to Proposed Amendment No. 3 to the Clonburris SDZ Planning Scheme concerning the proposed removal of the vehicular bridge over the railway including any associated appendices and modelling outputs. The report should also confirm the expected timeline for the Chief Executive's report following the consultation and how members will be informed of the next stages in the amendment process.
REPLY:
South Dublin County Council (SDCC) submitted the proposed amendments to the Clonburris SDZ Planning Scheme 2019 to An Coimisiún Pleanála (ACP) on the 11th of September 2025. The submission included the Bridge Removal Assessment Modelling Report prepared by SYSTRA, which assessed the transport implications associated with Proposed Amendment No. 3, including the proposed replacement of the vehicular railway bridge with a pedestrian and cycle bridge.
Following correspondence from ACP dated the 11th of June 2026, confirming that the proposed amendments were required to proceed as material amendments, SDCC undertook statutory public consultation pursuant to Section 170A of the Planning and Development Act 2000, as amended.
The public consultation commenced on the 31st of August 2026 and closed on the 29th of September 2026. The Proposed Material Amendments and supporting documentation, including the SYSTRA report, were made available for public inspection throughout the consultation period through the Council’s online consultation portal and at the designated public inspection locations in County Hall, Tallaght and Clondalkin Library. Please see file path: Clonburris Proposed Material Amendment to the Clonburris Strategic Development Zone Planning Scheme 2019 | South Dublin County Council's Online Consultation Portal
The full SYSTRA report can be provided to Members. The report is a standalone document and does not contain or reference any separate appendices. No separate appendices or additional modelling outputs accompanied the report submitted to ACP. The relevant modelling outputs are contained within the report itself.
A total of 54 valid submissions and observations were received during the statutory public consultation period. SDCC has prepared its Planning Authority Report on the submissions and observations received, which sets out the matters raised, the Planning Authority’s responses and its recommendation to ACP. The report is currently undergoing final internal review and will be submitted to ACP within the statutory deadline. For clarity, the SDCC report is not a Chief Executive’s Report. It has been prepared by SDCC, as Planning Authority, as part of the statutory process under Section 170A of the Planning and Development Act 2000, as amended. The final determination on the Proposed Material Amendments rests with ACP.
Following submission, ACP will consider the Planning Authority Report together with the submissions and observations received before making its final determination on the Proposed Material Amendments. No confirmed timeframe for the Commission’s determination has been provided at this stage.
Members will be updated following submission of the Planning Authority Report to An Coimisiún Pleanála and will be advised of the Commission’s determination once it has issued.