QUESTION NO.18

QUESTION: Councillor C. Brady

To ask the Chief Executive for an updated position on the taking in charge of Gandon Park (SDZ18A/0004), including the outstanding issues preventing completion, whether EV charging installations are among those issues, and the revised timeframe for completion.

REPLY:

In response to the Elected Member's question regarding the taking in charge of Gandon Park (Planning Reference SDZ18A/0004), the Council can advise that the Taking in Charge (TIC) process remains ongoing and Council officials continue to engage with the developer in relation to a very small number of outstanding matters that must be satisfactorily resolved before the estate can be considered for formal taking in charge.

One of the issues currently preventing completion of the process relates to a number of unauthorised Electric Vehicle (EV) charging installations located within the development. These installations have been placed on footpaths and within car parking spaces without the necessary approvals and do not form part of the infrastructure that was approved under the development's planning permission.

Over the past four months, the developer has been actively pursuing the removal of the unauthorised EV charging equipment. The developer has issued correspondence to the owners of the unauthorised installations requesting their removal and continues to engage with those parties in an effort to achieve compliance.

The Council cannot take private electrical equipment into its charge as part of the Taking in Charge process. It is essential that the Council ensures that no liability is transferred to the local authority in respect of privately owned and unauthorised electrical infrastructure. Accordingly, all such matters must be regularised and resolved prior to any consideration of the estate being taken in charge.

While significant progress has been made on the Taking in Charge process, it is not possible at this stage to provide a definitive timeframe for completion. Compliance with this particular aspect of the process is dependent on the actions of the small number of property owners responsible for the unauthorised EV charging equipment. The Council will continue to liaise with the developer and monitor progress towards resolution of the outstanding issues.

The Council remains committed to progressing the Taking in Charge of Gandon Park as quickly as possible once all outstanding requirements have been satisfactorily addressed.