MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE

Wednesday, October 28, 2026

QUESTION NO.2

QUESTION: Councillor D. Loftus

To ask the Manager for an update on the Collinstown Park pavilion projects which was Part 8 approved in 2024, including a timeline for expected construction start and finish date?

REPLY:

The pavilion programme was agreed to support sports participation and community health and wellbeing as well as access to recreation by providing changing facilities and secure storage for sports clubs and community groups.

A programme review identified a need for additional capital funding, which was approved and the programme provides changing facilities for adjacent pitches and other sports facilities at 10 locations:

Griffeen Valley Park’s pavilion is complete and handed over to SDCC. It is being activated and will open for bookings shortly. Corkagh Park’s pavilion is now being commissioned before moving to activation and will subsequently open for bookings.

Collinstown Park Pavilion will be delivered as part of a group of 5 Pavilions, the tenders for which are currently being finalised. Once complete, a timeline for all 5 Pavilions, including Collinstown, will be made available.