MOTION: Councillor Joanna Tuffy
Cathaoirleach's Business
To ask for a headed item on what happens next in relation to the Masterplan for Lucan House and that councillors have an opportunity to ask questions of the Manager presenting the headed item.
REPORT:
Following the successful completion of a procurement process, Stephen Foley Architects have been appointed as lead consultants for the project and are currently advancing the detailed design of the Lucan House Masterplan. This work will inform the future tourism, heritage and community use of the site and is progressing across all elements of the overall masterplan. As part of this process, the documentation required for the Part 8 planning process is currently being prepared, with the public display stage anticipated to commence in Q4 2026. This will provide an important opportunity for public engagement and feedback on the emerging proposals.
In parallel with the design process, a programme of priority conservation works is being advanced to protect and preserve the historic fabric of the estate. Essential repair works to the northern section of the roof have been successfully completed, while investigations into the remaining roof areas are ongoing. In addition, procurement has been finalised for conservation works to two sections of the historic boundary wall, with restoration works due to commence shortly. Subject to the necessary statutory approvals and processes, the first phase of works is anticipated to commence on site in Q2/Q3 2027. This phase will focus on enabling works and improvements to the outdoor elements identified within the Masterplan, enhancing access and the visitor experience while laying the groundwork for subsequent phases of development.
The project has also achieved an important milestone through the successful opening of the grounds to the public at weekends since May 2026. This initiative has been well received, providing limited public access to the estate and enabling visitors to engage with this important heritage asset. Opportunities to further expand public access will continue to be explored as the project progresses.
In terms of funding, the Council continues to actively pursue a range of potential funding opportunities to support the delivery of the Masterplan, including engagement with Fáilte Ireland and other relevant funding bodies. Funding requirements and opportunities will continue to be assessed as the project advances through the design, planning and implementation stages.
The request for a headed item is noted. Given the significance of the project and its importance as a future tourism, heritage and community asset, it is intended that a further update on the Masterplan will be provided to the Members in the coming months.