ADJOURNED MEETING OF COUNTY COUNCIL

Tuesday, September 19, 2006

QUESTION NO. 13

QUESTION: Cllr. Cathal King

To ask the Manager, how many new social housing units does he/she expect to be transferred from Developers to South Dublin County Council  in the next two months ( Sept/Oct ) and can he/she provide details of how many units in each development are expected?

REPLY:

 

The following is a breakdown of the units that have been handed over to date in the County and the units with anticipated handover dates within the next two months (Sept/Oct):  It is anticipated to handover a total of 470 units within the next two months.

TALLAGHT AREA

Completions in 2006:-

Total

No. of Units

Completion Dates

Fettercairn Village

9

February 2006

Fettercairn Village

9

May 2006

Deerpark ( Jo int Venture)

11

May 2006

Deerpark (Joint Venture)

14

August 2006

Sub Total

43

  On Site:-

Scheme Name

No. of Units on Site

Completion Dates

Avonbeg, Phase 3

47

In phases end September, 2006

Fortunestown B, Phase 2

66 (+52 Vol. Units)

Sept – October 2006  

Fortunestown B, Phase 4

120

October 2006

Deerpark ( Jo int Venture)

94

(In phases) Aug 2006

Daletree (Part 5/Joint Venture)

27

(in phases) October 2005

Brookfield Village+ Community Facility

16

September 2006 

Sub.Total

370 (+52 Vol. Units)

  

LUCAN / CLONDALKIN AREA

 Completions in 2006

Scheme Name

No of Units

Completion

Moorfield

9

January 2006

Ballyowen Hall (Part V)

8

January 2006

Shancastle

11

March 2006

Moorfield

21

February 2006

Shancastle

15

July 2006

Mayfield

36

August 2006

Total

100

On Site

Scheme Name

 

 

No. Of Units

 

 

Completion

 

 

Balgaddy “E” (SH 210)

 

 

100

 

 

Phased from Oct 2006

 

 

Sub Total                                       100