QUESTION: Councillor D. Richardson
"Can the Manager report on the upgrade works of Killinarden Park and Whitestown Stream walkway?"
REPLY:
The main enhancement project at Killinarden Park is complete, however some further work is to be carried out on the pitches to aid establishment. This work will include fertilising and aeration, and will be carried out during April.
Work is currently progressing on the Whitestown Greenway, providing a new green infrastructure corridor along the Whitestown Stream, between Killinarden Park and Sean Walsh Park. This project is nearing completion and will provide an off-road walking and cycling route from West Tallaght to the centre of Tallaght, with further links to the Dublin Mountains Way and the Dodder Greenway.