MEETING OF TALLAGHT AREA COMMITTEE

Monday, April 27, 2026

QUESTION NO. 4

QUESTION: Councillor A. Smyth

"To ask the Council for an update on the solar panel project and a timeline for completion of solar panels on community centres?"

REPLY:

SDCC’s programme to install solar PV on community centres and libraries is underway with an initial 10 buildings selected in the first package of works. One community centre was originally included for upgrade of solar PV but it has been confirmed that the existing solar PV in place is operational and to a suitable standard/capacity.

Works are proceeding on the 9 buildings. Data collection, preliminary design, site survey, detailed design, and ESB (NC7) applications have been completed, as listed in the table below.  Ballyroan Community and Youth Centre is currently at detailed design stage.

Of the 9 connection applications submitted to the ESB:

Pending approval of these applications, installation on site for these buildings is expected to begin the week commencing the 15th June 2026, with further installation dates in July and August 2026.

 

Building

Data Collection

Prelim Design

Site Survey

Detailed Design

ESB Connection

Installation

Monitoring/ Metering

1

Ballyroan Library

Completed

Completed

Completed

Completed

Awaiting confirmation of approval

 

 

2

Castletymon Library

Completed

Completed

Completed

Completed

In progress

 

 

3

North Clondalkin Library

Completed

Completed

Completed

Completed

In progress

 

 

4

Fettercairn CYC

Completed

Completed

Completed

Completed

Awaiting confirmation of approval

 

 

5

Ballyroan CYC

Completed

Completed

Completed

In Progress

 

 

 

6

Rowlagh CC

Completed

Completed

Completed

Completed

Awaiting confirmation of approval

 

 

7

Jobstown CYC

Completed

Completed

Completed

Completed

In progress

 

 

8

Quarryvale CYC

Completed

Completed

Completed

Completed

Awaiting confirmation of approval

 

 

9

Brookfield CYC

Completed

Completed

Completed

Completed

In progress

 

 

10

Firhouse CC

Completed

Existing PV operating correctly

 

 

 

 

 

11

Kilnamanagh CC

Completed

Completed

Completed

Completed

Approved