QUESTION: Councillor V. Casserly
To ask the manager for an update on completion date for Lucan Village Enhancement Scheme
REPLY:
Lucan Village Enhancement Scheme update
Village Green-
Works to complete
o Riverside painted metal and glass parapet
o Bandstand and lighting
o Grass sodding placed in pavers, 80% complete
o Landscaping along river wall, 30% complete
o River wall construction, 75% complete
Lucan Demesne
Overall 97% complete
Completion in Mid-April 2026
works to complete
Liffey Promenade
Lucan Bridge
To complement the village schemes, Lucan Bridge will receive periodic restoration and maintenance works by TRIUR Construction Limited, to commence in March 2026