QUESTION NO.1

QUESTION: Councillor V. Casserly

To ask the manager for an update on completion date for Lucan Village Enhancement Scheme

REPLY:

Lucan Village Enhancement Scheme update

 

Village Green-

 Works to complete

o   Riverside painted metal and glass parapet

o   Bandstand and lighting

o   Grass sodding placed in pavers, 80% complete

o   Landscaping along river wall, 30% complete

o   River wall construction, 75%  complete

Lucan Demesne

Overall 97% complete

Completion in Mid-April 2026

works to complete

Liffey Promenade

 

Lucan Bridge

To complement the village schemes, Lucan Bridge will receive periodic restoration and maintenance works by TRIUR Construction Limited, to commence in March 2026