QUESTION: Councillor C. Brady
To ask the Chief Executive to provide, in tabular format, the number of 1) requests received and 2) requests outstanding in the Local Electoral Area by location for (a) window and door replacements and (b) measures such as insulation and other works aimed at improving energy efficiency and reducing heating costs for tenants.
REPLY:
The Energy Efficiency Retrofit Programme (EERP) is due to run until 2030 with the aim of funding the retrofit of social homes requiring insulation and energy upgrade works. The locations for the EERP programme are determined by our technical team based on existing Building Energy Rating & building type with the project spread across our existing Housing Stock.
The council has commenced periodic property inspections, whereby properties will be inspected on a 5-year cycle. The findings of the surveys will feed into an ongoing multi-annual Stock Investment Programme which will include the Windows and Doors Programme.
The table below provides an update on the progress of the Windows and Doors Programme within the Lucan / Palmerstown / North Clondalkin LEA to date.
|
Area |
Pre-tender & Contractor stage |
Completed |
Total |
|
Lucan |
10 |
15 |
25 |
|
Palmerstown |
30 |
98 |
128 |
|
North Clondalkin |
8 |
83 |
91 |
|
Total |
48 |
196 |
244 |