COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

MEETING OF CLONDALKIN, NEWCASTLE, RATHCOOLE, SAGGART AND BRITTAS AREA COMMITTEE

Wednesday, November 19, 2025

QUESTION NO. 7

QUESTION: Councillor F. Timmons

To ask the Chief Executive for a report on behalf of Cherrywood Residents Group as to when the remaining lights will be replaced in Cherrywood estate? How many done and how many outstanding?

REPLY:

There are approximately 134 PL columns at Cherrywood that need alterations carried out with ESBN in order to allow us to upgrade to LED. 

Some of these require column replacements and the associated civil works.  We estimate we have 80% of these columns completed to date. 

Our target is to have the whole estate completed before the end of the year.