MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, October 13, 2025

QUESTION NO. 9

QUESTION: Councillor E. Ó Broin

To ask the Chief Executive to describe the work that has been carried out in 2025 to implement the Cycle South Dublin programme?

REPLY:

The Cycle South Dublin programme consists of 45 projects to be delivered as 63 schemes to provide a cycle network of 263km of high-quality cycle track by 2029.

This network will build on pre-2021 schemes such as the Grand Canal Greenway, Willsbrook Road, Monastery Road and the R120 new Nangor Road to Adamstown project amongst others. The developing network will link into future Bus Connect corridors connecting South Dublin into Dublin City Centre.

A significant number of projects have already been delivered under the Cycle South Dublin programme, this includes Sections 1 to 4 of the Dodder Greenway, Avonbeg Greenway, D24 neighbourhood Network Phase 1, D12 Bike Bus Route and others. At this point in time, 50% of the Cycle South Dublin network will be delivered or will be ready to commence works. Continued delivery of the Cycle South Dublin is dependent on significant annual funding provided by the National Transport Authority.

In addition to the active travel and cycle routes, the national “Safe Routes to School” and South Dublin “Safe School Zones” schemes are developed and delivered by the Active Travel section. These schemes and are included in Cycle South Dublin projects where schools are on, or adjacent to the Cycle South Dublin network. Current activity related to Cycle South Dublin is as follows.

Projects completed or due to be completed in 2025:

Projects currently under construction or ready to commence in 2025/early 2026:

Projects at design stage:

Projects at planning stage:

Projects at preliminary design stage: