COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE
Tuesday, September 23, 2025
QUESTION NO.11
QUESTION: Councillor C. Brady
To ask the Chief Executive for a report on the Lucan Leisure Centre project, confirming whether the tender process to appoint a contractor has been completed, and if not, the expected timeline for completion; and to outline the remaining tasks required to complete the project, including whether any sub-contractors are currently on site carrying out these tasks.
REPLY:
Following the termination of the contract with PJ McLoughlin on 22nd August 2025 an interim contractor from the maintenance framework has been appointed and is addressing snags from Phase 1 and progressing Phase 2 works.
We are in the process of preparing tender documents for the procurement of a replacement main contractor which will issue shortly.
Following receipt of tenders a replacement main contractor will be appointed to progress and complete finishing and commissioning works to handover Phase 2 -Swimming Pool
An update will be provided as soon as the final completion programme has been determined.