COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, September 08, 2025
QUESTION NO. 27
QUESTION: Councillor E. Ó Broin
Given the delays with the construction of Lucan Pool and the enhancement of both Corkagh and St Cuthbert's Parks, is there a pattern emerging with respect to how some private contractors implement contracts they win from SDCC?
REPLY:
All projects under South Dublin County Council’s remit are subject to strict oversight and monitoring throughout their construction phase. Any variance from the baseline programme is immediately flagged and interrogated by the relevant team in order to determine the most appropriate actions to mitigate any delay.
The three projects referred to have suffered delays due to a variety of causes as outlined below:
Considering the above, there is no evident pattern of behaviour which emerges when the reasons surrounding the delays are examined in detail. While delays to these projects are regrettable, they represent a small percentage of the projects being undertaken by South Dublin County Council.