QUESTION NO. 6

QUESTION: Councillor Y. Collins

To ask the Chief Executive for an update in relation to the number of public lighting outages in areas which have not yet been upgraded to LED lighting and the average timescale for repair

REPLY:

 

LEA

No. Of Outages as of 02/09/25

Clondalkin

128

Firhouse-Bohernabreena

28

Lucan

5

Palmerstown-Fonthill

28

Rathfarnham-Templeogue

53

Tallaght Central

55

Tallaght South

55

   
 

Total                                                  352

   

(which is 6% of our total remaining stock of  6,000 SOX fittings)

     

 

These repairs are all the older type orange low pressure sodium (SOX) fittings. The replacement lamps for these fittings are no longer available. If the lamps were available, the turnaround time between reporting of the outage to our maintenance contractor and the repair of the fitting is contractually 14 working days or less. As stated above, there are no lamps available on the open market.

The only option open to us is to use old lamps harvested from estates in the county that are being upgraded to LED. Due to resource issues within ESB Networks, the rollout of this upgrade programme has been seriously impeded.

Therefore it is difficult to forecast how many lamps we may or may not have available to us at any given time to carry out repairs, and as such, we cannot provide an average timescale for repair. However, we do try and address the oldest outages first.