COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE

Tuesday, June 24, 2025

QUESTION NO.9

QUESTION: Councillor C. Brady

To ask the CEO for an update on the Lucan Leisure Campus project, including progress to date, the status of remaining tasks, the projected timeline for opening, and the proposed membership pricing structure.

REPLY:

All elements of the Phase 1 areas are at or near completion. Tarmac and line marking to the car park and concrete paths to the entrance are complete. The ER/ Assigned Certifier has commenced the BCAR upload of completed certs.

On completion of upload (subject to contractor performance) this will be followed by Substantial Completion and handover to the operator.

For Phase 2 of the swimming pool, the contactor is to present a strategy and programme for review by Friday June 20th.

In order to drive progress we continue to apply substantial resources to site and those of the design team. We are directly engaging with more of the critical Sub-Contractors as far as we can under the contract.

Aura leisure have provided the below regarding the latest proposed pricing structure:

PAYG

Price

Adult Gym

€11.00

Student Gym (16+)

€8.00

OAP Gym

€6.00

Adult Swim

€10.50

Family Swim

€28.00

Child Swim (U-16)

€6.00

Student Swim (16+)

€8.00

OAP Swim

€6.00

Adult Gym & Swim

€12.50

Student Gym & Swim (16+)

€9.00

OAP Gym & Swim

€7.00

 

 

They note that pricing will be competitive and inclusive, with a range of concessions and community initiatives in place. These include, but not limited to: