COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF CLONDALKIN, NEWCASTLE, RATHCOOLE, SAGGART AND BRITTAS AREA COMMITTEE
Wednesday, January 15, 2025
QUESTION NO 4.
QUESTION: Councillor F. Timmons
To ask the Chief Executive for a detailed report into When will the Creshe be built in Graydon that includes who is responsible for delivery, How long does planning last? how long would construction take? And What developer will build the Creche?
REPLY:
A planning application (reference number SD22A/0459) was made by Cairn Homes in December 2022 for a 2-storey creche measuring 778 sq metres and sited within the Graydon development. This application was granted by SDCC in February 2023. An appeal was made by a Graydon resident against this decision. In April 2024, An Bord Pleanala upheld the decision of SDCC. The permission granted on appeal has the standard duration of 5 no. years and several compliance conditions that must be agreed prior to the commencement of development. Related compliance details have not yet been submitted for agreement prior to the commencement of development.