To ask the manager to provide an update in tabular format of all estates/locations listed in the 2023/2025 tree maintenance program and the status e.g. completed, scheduled and whether the programme will successfully complete all locations by the end of this year?

REPLY:

The table below sets out the detailed list of estates, roads and other locations which have been included on the current 3 year tree programme 2023 to 2025 for planned maintenance for the Lucan/Palmerstown/North Clondalkin area.  There are a total of 55 locations included on the programme with 16 of those completed to date. Maintenance works are currently underway in 4 locations.

Location

Status

Year

Adamstown Link Rd

In progress

2024

Abbeydale

Scheduled

2025

Abbeywood

Scheduled

2025

Ashpark street trees

Scheduled

2025

Ashpark Mature trees

Scheduled

2025

Bewley

Complete

2024

Brookvale

Scheduled

2025

Ballyowen Road - L1042 (Larkfield to Fonthill Road)

To be scheduled

2025

Corkagh Park (Mature trees)

Priority 1 complete

2024

Culmore Road and Park

Complete

2024

Castle Riada

Scheduled

2025

Castle Road

To be scheduled

2025

Coldcut Road

To be scheduled

2025

Dodsborough Road & Cottages on o/s

To be scheduled

2025

Elm estate street trees and mature trees

Scheduled

2025

Earlsfort

Complete

2023

Esker Road and Drive and L1011/Old Esker Lane

Scheduled

2025

Esker Glebe and Esker Lane O/S Mature trees

Scheduled

2025

Esker Glebe, The Glebe and Esker Lane street trees.

Scheduled

2025

Esker Park rear of houses on O/S (Additional)

Scheduled

2025

Esker Meadow

In progress

2024

Esker Woods

In progress

2024

Esker Lodge street and mature trees

Scheduled

2025

Fonthill Road and Coldcut Road cycle paths (Greenfort Boundary)

Scheduled

2025

Foxford and Ballyowen Lane

To be scheduled

2025

Fforster estate

Complete

2024

Foxdene

Complete

2024

Glenmaroon Road and Park

Complete

2024

Greenfort estate

Complete

2024

Griffeen Road, Avenue & Way

Complete

2024

Harelawn

Scheduled

2025

Hermitage Valley - Rear of Houses

Scheduled

2025

Hermitage Park - Mature Trees

Scheduled

2025

Lucan Road (Ballydowd to Woodies)

To be scheduled

2025

Liffey Estate

To be scheduled

2025

Manor Road and Park

Complete

2024

Meile an Ri

To be scheduled

2025

Newcastle Road/R120 to include Lucan Harriers car park frontage

Partially complete

2025

Neilstown estate

Complete

2024

Riversdale Estate Palmerstown

To be scheduled

2025

Riverside Drive

Complete

2024

Rochfort

In Progress

2024

Shancastle

Complete

2024

Saint Marks

Complete

2024

Saint Finians

Complete

2024

Sarsfield Park Mature Trees

To be scheduled

2025

St. Lomans Road (L1042) and Ballyowen Road

To be scheduled

2025

Tandys Lane Park (Additional)

Scheduled

2025

Tor an Ri

To be scheduled

2025

Turret Road

Complete

2024

Woodview Heights

To be scheduled

2025

Willsbrook Estate and Road

To be scheduled

2025

Wood Avens

To be scheduled

2025

Woodfarm Drive and Avenue

Complete

2024

Westbury

To be scheduled

2025