REPLY:

The Council has made commitments to deliver a series of new build community facilities and provide upgrades/extensions to a number of existing community centres, through budget provisions approved in the 3 Year Capital Programme. In addition, we continue to work on the progression of other ongoing and essential repair/upgrade projects to existing community facilities in the County.

The below table list the main community facility capital projects currently committed to and for the period 2025-2027 with indicative deliverly timelines:

Community Centre

Capital Works Description

Timeframe

Balgaddy CC

New Build

On site, anticipated completion late Dec 2024

Quarryvale CLC

Major Upgrades

On site, anticipated completion Jan 2025

Brookfield CYC

Roof Upgrade

On site, anticipated completion Dec 2024

Kilcarbery CC

New Build

Construction planned to commence Q1 2025

Killinarden (Foothills) CC

New Build

Construction planned to commence in 2025 as part of the Housing Development

Citywest CC

New Build

Design currently being finalised wiht revised planning permission to be submitted in Q1 2025

Citywest Youth Facility

Fit Out of Unit

Anticipated works to commence Q2 2025

Ballyroan CYC

Centre Extension

Part 8 scheduled for Jan 2025 and works to anticipated to commence in Q2 2025

Whitechurch Sports Facility

New Build

Part 8 scheduled for Q1 2025

The Park CC

Centre Extension

Part 8 scheduled for Q1 2025

Newcastle CC

New Build/Extension

Anticipated construction works to commence in 2026

Knockmitten CYC

Extension & Refurbishment

Anticipated works to commence in 2026

Perrystown Manor CC

Extension & Refurbishment

Anticipated construction works to commence in 2026