COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE
Tuesday, October 22, 2024
MOTION NO.10
MOTION: Councillor N. Fennell
This Committee agrees that the Manager produces a report for discussion for an update on new social housing builds in Balgaddy, Cloverhill , Clonburris and Adamstown
REPORT:
The table below sets out the delivery pipeline for new social housing builds currently under construction in Balgaddy, Cloverhill, Clonburris and Adamstown for 2024, 2025 and 2026. This is a combination of Council own build projects, turnkey acquisitions and housing delivery in partnership with the AHB sector.
Year | Project Name | Number of Units | Delivery Type | Status | AHB Partner | Comments |
2024 | Balgaddy | 69 | SDCC Build | On-site | N/A | Property breakdown: 45 x 3-Bed House,6 x 3-Bed Duplex, 1 x 2-Bed Duplex, 9x 1-Bed Duplex, 7x 2-Bed Apartment & 1 x 3-Bed Apartment.Three phase handover with all properties due in by 20/11/2024 |
2024 | Tandy's Lane, Adamstown | 3 | SDCC Acquisition | On-site | N/A | Property breakdown: 1 x 4-Bed House, 2 x 3-Bed House Properties due to be handed over mid November 2024 |
2024 | The Crossings, Adamstown | 30 | AHB CALF | Complete | Oaklee Housing | Property breakdown: 12 x 1-Bed Apartment & 18 x 2-Bed Apartment All properties handed over September 2024 and currently being tenanted |
2024 | Aderrig, Adamstown (Phase II) | 23 | AHB CALF | On-site | Cluid Housing | Property breakdown: 1 x 4-Bed House, 4 x 3-Bed House, 9 x 3-Bed Duplex, 9 x 2-Bed Apartment Properties due to be handed over mid October 2024 |
2024 | Hallwell, Adamstown (Phase II) | 64 | AHB CALF | On-site | Oaklee Housing | Property breakdown: 6 x 3-Bed Duplex, 4 x 2-Bed Duplex, 32 x 2-Bed Apartment, 22 x 1-Bed ApartmentProperties due to be handed over mid November 2024 |
2024 | Cloverhill Lodge, Clondalkin | 40 | AHB CALF | Substantially Complete | Oaklee Housing | Property breakdown: 38 x 3-Bed House, 2 x 2-Bed HouseProperties due to be handed over early November 2024. All properties have been allocated |
2025 | Canal Bank, Clonburris | 56 | SDCC Build | On-site | N/A | Property breakdown: 3 x 4-Bed House, 3 x 3-Bed House, 8 x 3-Bed Duplex, 8 x 2-Bed Duplex, 34 x 1-Bed Apartment Construction progressing in line with programme. This scheme also includes 60 Affordable Purchase Homes. |
2025 | Tandy's Lane, Adamstown | 15 | AHB CALF | On-site | North & East Housing Association | Property breakdown: 3 x 4-Bed House, 9 x 3-Bed House, 3 x 2-Bed HouseConstruction progressing in line with programme |
2026 | St Helen's Plaza, Adamstown | 80 | AHB CALF | On-site | Tuath Housing | Property breakdown: 24 x 2-Bed Apartments, 56 x 1-Bed ApartmentsConstruction progressing in line with programme |
2026 | Somerton Gate, Adamstown | 68 | AHB CALF | On-site | Cluid Housing | Property breakdown: 19 x 2-Bed Apartments, 49 x 1-Bed ApartmentsConstruction progressing in line with programme. This will be an age-friendly development |