COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE

Tuesday, September 24, 2024

QUESTION NO.27

QUESTION: Councillor L. O'Toole

Could the Chief Executive provide an update on the progress of the permanent school build on the lands of SDZ Clonburris (Griffeen CC) ? It has been observed locally in recent weeks that some preliminary work has begun. Any clarification the Council could provide regarding the current status and next steps would be greatly appreciated.

REPLY:

Following recent meetings on school delivery with the Department of Education, the status of the Griffeen CC project, as of the 31 August 2024 is indicated as Stage 3 (Tender Stage).
The current works in the area are the progression of undergrounding of the overhead lines to facilitate the school.