COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, July 08, 2024
QUESTION NO. 13
QUESTION: Councillor W. Carey
To ask the Chief Executive if he can offer a detailed list of traffic and community projects that are being delayed due to failure of ESB to install connections to the network.
REPLY:
The attached report provides detail on the current status of ESB connection applications that are currently outstanding for the completion of new pedestrian crossings across the County.
SDCC have been contacting ESB on a weekly basis to expedite the number of connections delivered.
SDCC have been assured that our power connection applications will be reprioritised within the ESB work delivery programmes. This is hoped improve the speed of the ESB connections delivered for SDCC going forward.