COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, April 08, 2024
QUESTION NO.4
QUESTION: Councillor T. Costello
To ask the Chief Executive for an update on projects that were awarded sports capital funding in the past 5 years
REPLY:
REPLY:
The Sports Capital Programme update below outlines the total number of projects in progress, completed and not commenced in the County. The Public Realm team manage some of the projects under the Capital Programme, while the Community team support the community facilities that have a direct landownership link to the Council.
Sports Capital Programme |
2015 |
2017 |
2019 |
2020 |
Total Number of Projects |
5 |
8 |
9 |
18 |
Completed |
3 |
1 |
1 |
6 |
In Progress |
1 |
7 |
7 |
11 |
Not Commenced |
1 |
0 |
1 |
1 |
The Council is currently awaiting a decision from the Department of Tourism, Culture, Arts, Gaeltacht, Sport and Media, in relation to the 34 projects and over €2.7 m applied for under the Sports Capital and Equipment Programme (SCEP) 2023.