QUESTION NO.6
QUESTION: Councillor P. Gogarty
To ask the Chief Executive to report on progress at Lucan Pool site since the site meeting on 20th January last, including updates on the delivery and installation of the moveable floor, the main screeding of the pool, tiling packages, the Irish Water drainage connection and to outline whether any new certainty has been given on completion dates?
REPLY:
The movable floor has been delivered and installed. The screeding to the pool is complete.
The tiling to the multi-functional pool and the floor of the main pool is complete and grouted.
Tiling to the walls of the main pool is underway. Grouting to the floor tiles of the changing village is underway.
SDCC have requested that Irish Water review the foul connection issue and address. IW have suggested arranging another meeting with the designers to progress/resolve this issue. SDCC have instructed their design team to engage further.
Completion date remains under review and the progress on site is being assessed to inform same. SDCC will advise in the coming weeks of the expected completion date following completion of the project milestones outlined during the site visits carried out on 26th January & 2nd February.