QUESTION NO.12
QUESTION: Councillor S. Moynihan
To ask the Chief Executive to provide an overview of the number of houses in Lucan, Palmerstown and North Clondalkin that are ready to be occupied but have not been connected to utilities and to present these by development.
REPLY:
The handover of 38 units at the St Marks/Rowlagh scheme has been subject to delays with works relating to utilities which has in turn delayed completion of related external works including roads, footpaths, and landscaped areas. All utilities have now been connected and commissioning works are in progress.
Our project team are actively engaging with the contractor and other stakeholders to arrange handover of the scheme and to facilitate occupancy of the new homes as soon as possible.
The handover of 40 units at Cloverhill Road, Clondalkin have also been subject to delays in connection to the ESB network. Our AHB partners are working closely with the ESB to facilitate connection with a view to handover in the coming weeks.