COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, February 26, 2024
QUESTION NO.
QUESTION: Councillor M. Duff
"Can the Manager make a report to this Area Committee as to when the upgrade works, outside the main entrance to County Hall and Library Square, will be completed?"
REPLY:
The Tallaght Public Realm project is nearing completion. The works contractor has undertaken to complete the overall contract by the end of April. The area directly around County Hall will be completed ahead of this and is projected for completion by the end of March (subject to the weather permitting ongoing soft planting).