QUESTION NO. 10
QUESTION: Councillor L. Hagin Meade
To ask the manager, in tabular form, the average waiting times for maintenance repairs to be completed for social housing tenants in SDCC during 2023?
REPLY:
The Council categorises all requests for repairs depending on the nature of the problem. These categories are emergency, urgent, routine or cyclical.
Every effort is made to respond to requests for repairs according to the guidelines below:
CATEGORY |
TIMESCALE |
EXAMPLE |
Emergency |
1 – 5 working days |
Smoking Fuse Board, Burst water tank |
Urgent |
10 working days |
Leak under sink unit, Leaking roof |
Routine |
12 weeks + |
Replace toilet cistern, Faulty radiator |
Cyclical |
1 – 7 years |
Leaking gutters, replacement hall door etc. |
11,640 work orders were completed in 2023 as detailed in the table below:
Category |
No. of Work Orders Complete |
Average No. of Days to complete |
Electrical |
900 |
9.59 |
Mechanical |
4299 |
3.99 |
Plumbing |
4961 |
35.23 |
Miscellaneous |
1480 |
36.26 |
The Council has recently increased the number of contractors engaged to carry out response maintenance works from 2 to 5, this should reduce our average response maintenance times.