COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE
Tuesday, December 19, 2023
QUESTION NO. 2
QUESTION: Councillor D. Ó Brádaigh
To ask the manager to provide an update on the progress of the SDCC windows and doors replacement programme. Report to include numbers approved, applications pending inspection, estimated timeline between decision and works being carried out and broken down by LEA.
REPLY:
The Council is currently replacing windows and doors under a number of funding programmes. In each case, the funding provided is on a county wide basis and is allocated to properties based on an established need rather than a geographical location. The options for replacing windows and doors currently are as follows.
Please see breakdown below of the current status of the windows and doors programme across all Electoral areas:
Electoral Area |
Works Complete |
Contactor Appointed |
At Tender Stage |
Totals |
Clondalkin |
38 |
24 |
29
|
91
|
Lucan |
5 |
5 |
0 |
10
|
Palmerstown/Fonthill |
56 |
19 |
5 |
80
|
Rathfarnham Templeogue |
7 |
2 |
35 |
44
|
Tallaght Central |
31 |
21 |
33 |
85 |
Tallaght South |
90 |
10 |
155 |
255 |
Firhouse-Bohernabreena |
8 |
1 |
6 |
15 |
Total |
209 |
113 |
258 |
580
|
A review of the remaining properties to be completed under this programme is underway but it is anticipated that 200 properties countywide will be issued for completion in 2024.
Once these works are complete, this specific programme will end.
2.Emergency Works are carried out on properties where due to the current condition of the windows; a safety risk is evident.
3.Windows and Doors typically form part of the work under the Energy Retrofit Programme. Funding is allocated annually by the Department of Housing, Local Government and Heritage. Going forward, this will be the main source of funding used to replace windows and doors. In order for the replacement to take place, other upgrade works, including insulation, heating and ventilation, will be carried out at the same time. Tenants will be required to agree to all aspects of the works, in particular the conversion of existing gas and oil heating systems to more energy efficient low pollutant option, such as air to water heat pumps. The overall aim of the scheme is to carry out upgrade works to the building fabric and heating systems to achieve a minimum Building Energy Rating of B2. Housing Maintenance are currently working to expand the availability of contractors to allow for additional capacity to deliver the works required subject to availability of funding.