COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, November 27, 2023
QUESTION NO. 6
QUESTION: Councillor C. O'Connor
"To ask the CEO to present an update on Relets and in reporting will he list the number of such properties in Tallaght estates and detail the actions being taken and will he make a statement?"
REPLY:
The following is the current status of the vacant properties within our Council housing stock.
Electoral Area |
To Survey |
In Progress |
Ready |
TOTAL |
Lucan |
1 |
0 |
1 |
2 |
Clondalkin |
0 |
3 |
0 |
3 |
Palmerstown-Fonthill |
4 |
9 |
5 |
18 |
Tallaght South (N) |
3 |
10 |
5 |
18 |
Tallaght South (S) |
0 |
5 |
6 |
11 |
Tallaght Central |
0 |
6 |
1 |
7 |
Firhouse-Bohernabreena |
0 |
1 |
1 |
2 |
Rathfarnham-Templeogue |
0 |
0 |
1 |
1 |
TOTAL |
8 |
34 |
20 |
62 |
Of the 34 properties were works are in progress, 29 are expected to be complete in the coming 4 weeks with the remaining 5 properties to be completed in the next 8 weeks. A total of 178 properties with an average turnaround time from vacant to relet for year to date, is 26.6 weeks.
Is should be noted that the turnaround time for October was 22.8 weeks.