COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE
Tuesday, October 24, 2023
MOTION NO. 16
MOTION: Councillor V. Casserly
Cathaoirleachs Business
This area committee calls on the manager and law agent to present penalties and actionable measures taken with PJ McLoughlin services for the ongoing delays and long awaited build of the Lucan Swimming Pool.
REPORT:
The Council has received a revised contractor programme showing a completion date for December 2023, this is currently being examined by the project managers to confirm its feasibility and it is now our intention to pursue appropriate remedies available under the building contract for any unjustified delays over and above the previously submitted programme. It would not be appropriate to provide any further comment at this time.