"To ask the Manager, when will the next phase for Whitestown Stream commence?"

REPLY:

Whitestown Stream phase 1 has been completed and this work has consisted of boundary treatment works, installation of entrances as well as footpath tie-ins. The tender for phase 2 of the scheme has now been concluded and the preferred bidder has been awarded the contract. The provisional start date for phase 2 works at the Whitestown Stream is November 6th, these works are expected to be completed by the end of July/ August 2024.