COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF TALLAGHT AREA COMMITTEE

Monday, September 25, 2023

QUESTION NO.

QUESTION: Councillor C. O'Connor

"To ask the CEO to present a detailed update on all the works being carried out at Tallaght Stadium; will he understand the concerns that the works be completed without delay; will he give assurances and make a statement?"

REPLY:

As previously advised, the Contractor ABM Design and Build Ltd. has provided an updated construction programme and it is expected that the North Stand will now be fully completed during Q3 2023. Sign off on completion is subject to BCAR certification.  The completion of the new Stand is delayed by a number of weeks due to unanticipated supply chain issues in the delivery of some materials being used in the construction of the new stand but remains on target for late October.

The progress of the project is monitored closely to ensure timelines are met and this will remain the case.