COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF HOUSING SPC

Thursday, September 14, 2023

HEADED ITEM NO. 6 (iii)

HEADED ITEM: H. Administration

Relets Update 

140 Council-owned, vacant social homes have been allocated in the period January to August 2023 with an average turnaround time of 25.11 weeks.  There are currently 80 vacant properties at various stages of re-let works. This represents a 27% reduction in the number of vacant properties since May 2023.

The current status of these properties by local electoral area and relevant stage of the re-let process is shown below: 

Electoral Area

 

Survey

On Hold

In Progress

Ready

Total

Lucan

0

1

1

2

4

Clondalkin

1

1

1

3

6

Palmerstown-Fonthill

1

4

12

6

23

Tallaght South 

2

0

21

9

32

Tallaght Central

2

0

5

4

11

Firhouse-Bohernabreena

0

0

2

0

2

Rathfarnham-Templeogue

0

0

0

2

2

Total

6

 

6

42

26

80

Of the 42 properties in progress, works are scheduled to be completed on 32 properties in the coming 4 weeks with the remaining 10 properties to be completed in a 4-to-8-week period.