QUESTION NO. 20

QUESTION: Councillor C. O'Connor

To ask the CEO to present an update on the Relets programme and will he give details on houses involved across the County and will he make a statement?

REPLY:

The following is the current status of the vacant properties within our Council housing stock.

Status

No. Properties

Works to be issued to contractors

10

Work in Progress

59

Works Complete

26

Total

95

Of the 59 properties were works are in progress, 41 are expected to be complete in the coming 4 weeks with the remaining 18 properties to be completed in the next 8 weeks. A total of 97 properties with an average turnaround time from vacant to relet for year to date, is 27.5 weeks.

It should be noted, in November 2022, a report was issued to the Housing SPC of the findings of a review of the Housing Maintenance Re-Let Process.  The aim of the review was to find efficiencies to reduce the length of time to complete necessary maintenance works to allow the properties to be re-allocated to new tenants.  In turn this would reduce the number of properties vacant at any point in time.  Based on findings of the review, the following has been implemented.

Following the implementation of the review, Housing Maintenance Section would like to highlight significant improvements in the delivery of vacant properties over Q2 2023.

Housing Maintenance acknowledges the work to date is not yet reflected in the turnaround times, from vacant to relet.  It is expected due to the progress on site seen in Q2, this will result in improvements in turnaround times during Q3-2023.

Status

Date

Comment

1/3/2023

30/6/2023

No. of Properties awaiting contractor appointment

55

10

Number of properties awaiting works schedules to be issued has reduced by 72%

Work in Progress

41

59

Number of properties where works is in progress has increased by 43%

Works Complete

25

26

Properties completed and not allocated remains static.

Total

121

95

Number of properties vacant reduced by 23%