COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, July 10, 2023

QUESTION NO. 8

QUESTION: Councillor L.Guéret

To ask the Manager for a report on building works on social housing developments, report to include if there are sites where works are currently not operational, if there are plans for work to resume in quarter 3 or quarter 4 at these sites?

REPLY:

The table below details social housing developments currently on site and the status of each development:

  

Site

No.

Update

Projected Completion

Old Bawn (age friendly)

12

On site

Aug ‘23

Maplewood (AHB, age friendly)

17

On site–completion date advised by AHB

Aug ‘23

Fernwood (AHB, age friendly)

23

On site–completion date advised by AHB

Nov ‘23

Riversdale Phase 2

18

On site

Nov ‘23

Whitestown (AHB, age friendly)

81

On site–completion date advised by AHB

Dec ‘23

New Nangor Road

93

On site

Dec ‘23/Q1 ‘24

Lindisfarne

19

On site

Q2 ‘24

Balgaddy

69

On site

Q2 ‘24

Homeville

16

Contractor appointed to resume works in August'23.

Q2 ‘24

St Aongus (age friendly)

12

Tender work progressing to appoint contractors and progress to site commencement in Q4 of this year.

Q3 ‘24

St. Ronan’s (age friendly)

9

Q3 ‘24

Pearse Bros Park(age friendly)

10

Q4 ‘24