QUESTION NO. 8
QUESTION: Councillor L.Guéret
To ask the Manager for a report on building works on social housing developments, report to include if there are sites where works are currently not operational, if there are plans for work to resume in quarter 3 or quarter 4 at these sites?
REPLY:
The table below details social housing developments currently on site and the status of each development:
Site |
No. |
Update |
Projected Completion |
Old Bawn (age friendly) |
12 |
On site |
Aug ‘23 |
Maplewood (AHB, age friendly) |
17 |
On site–completion date advised by AHB |
Aug ‘23 |
Fernwood (AHB, age friendly) |
23 |
On site–completion date advised by AHB |
Nov ‘23 |
Riversdale Phase 2 |
18 |
On site |
Nov ‘23 |
Whitestown (AHB, age friendly) |
81 |
On site–completion date advised by AHB |
Dec ‘23 |
New Nangor Road |
93 |
On site |
Dec ‘23/Q1 ‘24 |
Lindisfarne |
19 |
On site |
Q2 ‘24 |
Balgaddy |
69 |
On site |
Q2 ‘24 |
Homeville |
16 |
Contractor appointed to resume works in August'23. |
Q2 ‘24 |
St Aongus (age friendly) |
12 |
Tender work progressing to appoint contractors and progress to site commencement in Q4 of this year. |
Q3 ‘24 |
St. Ronan’s (age friendly) |
9 |
Q3 ‘24 |
|
Pearse Bros Park(age friendly) |
10 |
Q4 ‘24 |