COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF LUCAN / PALMERSTOWN / NORTH CLONDALKIN AREA COMMITTEE

Tuesday, April 25, 2023

QUESTION NO.7

QUESTION: Councillor M. Johansson

To ask the Chief Executive about the reasons for the delays on the new housing in St Mark's/Rowlagh (originally due to be completed in 2022)?

REPLY: 

The handover of the scheme at St Marks/Rowlagh has been subject to delays with works relating to utilities which has in turn delayed completion of related external works including roads, footpaths, and landscaped areas.

Our project team are actively engaging with the contractor and other stakeholders to arrange completion of the external works to facilitate occupancy of the new homes as soon as possible.