COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, December 19, 2022
QUESTION NO. 12
QUESTION: Councillor L. Dunne
"To ask the Chief Executive for an update on the Killinarden Park upgrade and for a time frame on when works will commence?"
REPLY:
The detailed design of the park is now complete, based on the Part 8 propsoals. Public Realm have also achieved approval in principle for funding from the National Transport Authority; which is very welcome; in delivering the active travel routes / lit shared route through the park. The tender package is also completed and the entire construction package is now out to tender. Subject to a successful tender process, it is hoped to start the construction works in the early part of 2023; (programme to be agreed with the successful contractor).