MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, December 12, 2022

QUESTION NO. 10

QUESTION: Councillor Lyn Hagin Meade

To ask the Chief Executive for an update on the retrofitting programme of SDCC owned homes, completed and planned, including the types of improvements made to the houses.

REPLY:

The table below shows a breakdown of the Council-owned properties with works completed or scheduled under the nationally funded Energy Efficiency Retrofit Programme (EERP).  Prior to works commencing, the building energy rating (BER) for the properties is typically in the range D4 to C3 and the objective of the EERP is achieve a minimum B2 BER or the cost optimal equivalent.  The works involved include:

The current status of works to properties inditified for inclusion under the programme to date is as follows:

Estate

EERP Year

No. Properties

Status

Comment

Cushlawn

2021

31

Complete

Post-works BER certs complete

Kilmahuddrick

2021

18

Complete

Post-works BER certs complete

Greenfort

2021

15

Complete

Post-works BER certs complete

Liscarne

2021

11

In Progress

5 properties complete and only heat pumps outstanding to be installed in remaining 6 properties in January 2023.

Cushalwn

2022

57

In Progress

Scheduled for completion Jan 2023

Castletymon

2021/2022

18

Tender Awarded

Works scheduled to commence January 2023

Allenton

2021/2022

53

Tender Awarded

Works scheduled to commence January 2023

Greenfort

2022

30

Tender Awarded

Works scheduled to commence January 2023

Limekiln

2022

8

Tender Aawarded

Works scheduled to commence January 2023

Sarsfield

2021

16

Pre-Tender

Tender documentation being finalised to issued Jan 2023 with works projected to commence March 2023

Willbrook

2021

4

Pre-Tender

Tender to be issued January 2023 with works projected to commence March 2023

St. Maelruan's

2023

4

Pre-Tender

Pre-tender BER assessments being carried out to inform tender documentation

Limekiln (Ph2)

2023

8

Pre-Tender

Pre-tender BER assessments being carried out to inform tender documentation

Oldcastle (TA)

2023

13

Pre-Tender

Pre-tender BER assessments being carried out to inform tender documentation

Kilmahuddrick

2023

34

Pre-Tender

Pre-tender BER assessments being carried out to inform tender documentation

Shancastle

2023

20

Pre-Tender

Pre-tender BER assessments being carried out to inform tender documentation

Tymon North/St Aongus

2023

23

Pre-Tender

Pre-tender BER assessments being carried out to inform tender documentation

Total

 

363