MOTION NO. 25
MOTION: Councillor L. O'Toole
This committee requests that the Chief Executive provides details on the proposed road layout to allow for the implementation of the construction traffic management plan as part of the Clonburris SDZ. To include all the roads (within the Lucan area) that will be used to accommodate construction traffic and similarly ask that a recap on the construction traffic management plan within Adamstown SDZ. To ask that a map identifying the roads accompany the response.
REPORT:
Section 2.9.13 of the Clonburris Planning Scheme states that a Construction Environmental Management Plan (CEMP) shall be prepared in advance of the physical elements proposed as part of the Planning Scheme and will be implemented throughout.
The Scheme outlines that CEMPs typically provide details of intended construction practice for the proposed development, including the following extracts:
- details of the timing and routing of construction traffic to and from the construction site and associated directional signage, ad
- measures to obviate queuing of construction traffic on the adjoining road network
A Construction Management Plan or CEMP will be approved by the LA on a case by case basis as each planning application comes forward for commencement. The haul routes agreed must be proven to have suitable capacity and be designed to facilitate HGV traffic.
SDCC cannot analyse the suitabilitly of proposed construction management plans until they are submitted and until the estimated haulage tonnage calculated and the frequency of loads from particular sites in Clonburris is known.