QUESTION: Councillor Shane Moynihan
To ask the Chief Executive for an update on retrofitting works on Council houses in the Lucan/Palmerstown/North Clondalkin area over the past twelve months.
REPLY:
Over the past 12 months, Housing Maintenance have been dealing with 92 properties in the energy efficiency retrofit programme in the Lucan/Palmerstown/North Clondalkin. The aim of the programme is to improve the properties energy rating to a minimum of B2 standard. Typical works include replacement of windows and doors, improvements to the insulation of the building fabric and installation of energy efficient heat pumps. The properties are at various stages from survey to completion. The following is the break down of the progress to date.
Estate |
Programme year |
No. of Properties |
Stage |
Comment |
Greenfort |
2021 |
15 |
Works Complete |
Post BER Certs being completed |
Greenfort |
2022 |
30 |
Tender closing 25/10/2022 |
On site November 2022 |
Liscarne |
2021 |
11 |
On Site |
Works complete on 5 properties with 6 heat pumps to be installed to complete remaining properties |
Sarsfield OAP |
2021 |
16 |
Tender to be issued week commencing 24/10/2022 |
On site December 2022 |
Shancastle |
2023 |
20 |
Tender to be issued November 2022 |
BER surveys have commenced. On site early 2023. |