COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF CLONDALKIN AREA COMMITTEE
Wednesday, May 18, 2022
QUESTION NO.16
QUESTION: Councillor William Joseph Carey
To ask the manager for an update on the tendering process for St Cuthberts Park Development?
REPLY:
The tender process has been completed and Nicholas de Jong Associates, have been appointed to carry out the St Cuthberts Park Masterplan.
The consultants have been requested to submit a detailed works programme as a first task, and we expect this to detail that the Community/Stakeholder Consultation will commence in June with a preliminary design and masterplan for the park completed by September/ October. The Pre-Part 8 presentation to the Council/ACM will be after that and allow Part 8 public consultation with decision by the Council thereafter. Councillors will be informed of the agreed timeline as soon as it has been agreed with the Consultants.