COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF RATHFARNHAM / TEMPLEOGUE / FIRHOUSE / BOHERNABREENA AREA COMMITTEE
Tuesday, April 12, 2022
QUESTION NO. 3
QUESTION: Councillor Yvonne Collins
To ask the Chief Executive for a comprehensive progress update as regards the works on the Grange Road cycle track and insofar as possible a definitive end date in relation to same
REPLY:
Following the update at the Decemebr 2021 Area Meeting, we can confirm that significant progress has been made on the resolution of the services and ESB issues encountered.
In the coming weeks, the ESB will make significant progess by undergrounding the overhead cables and new public lighting will be installed.
Resurfacing of the existing carraigeway is due to commence in mid-May.
The project is approaching completion and the expected completion date for these works is end of May 2022.