Progress on development of the Council’s large sites is as follows:
There are also currently 16 social housing construction projects in the Council's build pipeline (including four Council supported AHB schemes for priority needs accommodation) with projected delivery of 478 new homes from 2022 onwards as follows:
Project | No. | Update |
Fernwood/Maplewood*AF | 40 | Due for practical completion in Q2 but there are on-site delays that are being taken up with Clúid and the contractor. |
Riversdale, Clondalkin | 43 | Phase 1 of 25 homes on site & due for practical completion by June 2022. Contractor appointed for invasive species removal works for phase 2. |
Watercourse Grove, Homeville | 16 | Contractor issues are delaying progress - revised completion date to be confirmed. |
St. Catherine’s Way, Knockmore | 12 | On site and due for practical completion in Oct 2022. |
Templegoue Village*AF | 10 | On site & due for practical completion in Q1 2023. |
Whitestown Way*AF | 81 | On site & due for practical completion in Q1 2023. |
Old Nangor Road | 10 | Details of updated contractor programme awaited from Dublin Simon followign re-tender. |
Balgaddy | 69 | Tender issued with closing date in April 2022. |
St. Mark Ave* inc. 9 AF homes | 38 | On site & due for practical completion in Q4 2022. |
Eircom Site/Nangor Road | 93 | Site works commenced in March 2022 with projected practical completion by September 2023. |
Old Bawn (Brady’s Field)*AF | 12 | Tenders being assessed to prepare Stage 4 DHLGH funding report and to appoint contractor. |
Lucan Road, Palmerstown*AF | 4 | Tender process underway with Túath Housing advising likely completion date in 2023. |
Grand Canal Lindisfarne | 19 | Tenders being assessed to prepare Stage 4 DHLGH funding report and to appoint contractor. |
St. Aongus' Green | 12 | Design team being procured to progress detailed design and tenders. |
St. Ronans Crescent | 9 | Design team being procured to progress detailed design and tenders. |
Pearse Brothers Park | 10 | Design team being procured to progress detailed design and tenders. |
In addition, preliminary initial design work is progressing on a number of additional sites proposed in the Council's draft Housing Delivery Action Plan 2022-2026, namely Alpine Heights, Deansrath/Melrose, Castlefield, Kilcarbery 2 and Oldcastle Park, with a view to presenting proposals to local Area Committees later this year.