QUESTION NO. 10

QUESTION: Councillor Eoin Ó Broin

"To ask the Chief Executive for an approximate timeline for the delivery of the Community centre, creche facilities & retail units in Kilcarbery?"

REPLY:

The creche facility at Kilcarbery is scheduled to commence construction in Q3 2022 with a scheduled 11-month build programme and so it should be complete in Q2 2023.  The community centre is proposed for the final phase of construction in the development and is anticipated to commence in late 2023/early 2024.

Separately, the adjacent, proposed retail site is planned to be advertised for expressions of interest next month with a preferred bidder potentially selected in Q2 202, followed by a provisional 24-month timeline for delivery incorporating planning and construction.