QUESTION: Councillor P. Gogarty
To ask the Chief Executive for an update on the expected completion date of the electric gates at Lucan Harriers/Weston/AGP clubhouse and car park?
REPLY:
The request to provide power to the automated gate at Newlands Road was referred to ESB Networks following completion of the gate installation in July 2021. ESB Networks have been contacted to request an update on connection however to date this has not been provided. Once the power is connected the gate will be commissioned. In the meantime the area where the works occurred were recently resurfaced in preparation of commissioning