QUESTION NO.

QUESTION: Councillor T. Costello

To ask the manager for an update on the status of items which were on the Public Realm 2021 Programme of Works for Tallaght, which ones have been completed and which are outstanding and what is the expected timeline for completion.

REPLY:

An update on the status of each of the approved schemes is included below.  The following points add some additional information in relation to a number of the approved schemes -

1

Kingswood Crescent

Path between Kingswood Crescent and Kingswood Dale along the desire lines

Order issued, works to be carried out in November/December

2

Ballymount Park pitch 94 (GAA)

Drainage Works

Order issued however work will not commence until Spring 2022 due to current ground conditions.

3

Ballymount Park

Lake edge erosion protection

Completed.

4

Ballymount Park

Upgrade benches

Completed.

5

Bolbrook, Scoil Santain

Overlay footpaths as required

Completed.

6

Lios na Sidhe, Old Bawn Esate

Public Lighting scheme along open space

Order issued, works will commence in January ‘22

7

Dodder Valley Park Aylesbury

Footpath connecting Aylesbury to Seskin View

Completed.

8

Kilnamanagh to Greenhills Road

Public lighting scheme along new footpath

Order issued, works will commence in January ‘22

9

De Selby/N81 access

Install pedestrian barrier

Completed.

10

Dodder Valley Park Overlay river

Overlay footpath adjacent to the river

Commenced and will be completed in November/December

11

Tallaght Village

Pollinator planting scheme in large planter on Main St

Completed.

12

Dodder Valley Park Pollinator

Pollinator planting scheme adjacent to pavilion

Completed.

13

Sean Walsh Park

Plant pollinator friendly hedge

To be done in winter planting season in November/December

14

Belgard Square North/East junction

Upgrade roundabout with pollinator planting scheme

On hold for now due to Heatnet works

15

Aylesbury open space

Complete looped footpath

Footpath adjacent to community centre completed, loop is now in place including public footpath on Firhouse Road West

16

Avonmore/SeskinView/Bolbrook

Pollinator planting scheme

Completed.

17

Aylesbury Heatherview

Footpath from Heatherview Close to Heatheriew Drive

Completed.