QUESTION NO.13

QUESTION: Councillor C. O'Connor

To ask the Chief Executive to present an update on all current Council Housing projects throughout our County; will he details new completion dates where Covid restrictions have impacted on building programmes and will he make a general statement? 

REPLY:

Many of this Council's approved housing developments were completely closed down for significant periods during Covid-related restrictions and this has obviously impacted on projected completion dates for schemes.  In addition, the construction sector is currently experiencing numerous challenges relating to labour and materials that may impact on projects and the Elected Members will be kept updated in this regard as necessary. 

The Council's current approved housing construction projects and their status including projected completion dates are as follows:

Site

No.

Update

Fernwood/Maplewood

40

(Clúid Housing) Site start Q3 2020 - Clúid Housing recently advised updated projected completion date in Q2 2022.

Riversdale, Clondalkin

43

Site start Nov 2020 for phase 1 of 22 homes. Projected for completion in Q2 2022.

Watercourse Grove, Homeville

16

Site start Nov 2020 & projected for completion in Q2 2022.

St. Catherine’s Way, Knockmore

12

Site start Nov 2020 & projected delivery in Q2 2022.

Greenfort Gardens

2

Site start Nov 2020 and scheduled for completion Q4 2021.

Templegoue Village

10

Contractor appointed and doing pre-commencement design work - projected for delivery in Q4 2022.

Whitestown Way

81

(Clúid Housing) Site start Q2 2021 with projected delivery Q1 2023.

Old Nangor Road

10

(Dublin Simon) Stage 4 approval from DHLGH and site start pending with scheme projected for delivery by Q4 2022.

Balgaddy

69

Tender to be advertised November 2021.

St. Mark Avenue

41

Construction to commence October 2021 with projected delivery in Q4 2022.

Eircom Site/Nangor Road

93

Tenders completed & contractor to be appointed in Q4 2021 subject to DHLGH  approval

Old Bawn (Brady’s Field)

12

Tender to be advertised November 2021

Lucan Road, Palmerstown

4

Part 8 approved September 2020 / Túath Housing.  Tender assessment underway with projected site start Q1 2022 and completion in Q4 2022.

Grand Canal Lindisfarne

19

Tender to be advertised in December 2021.

St. Aongus' Green

12

Part 8 approved & detailed design commencing.

St. Ronans Crescent

9

Part 8 approved & detailed design commencing.

Pearse Brothers Park

10

Part 8 approved & detailed design commencing.

Total

483

 

In addiiton, the position relating to the various mixed tenure sites previously signalled to the Elected Members is as follows:

Kilcarbery: includes 310 social homes - commenced construction in April 2021 with initial tranche of homes due for completion in mid-2022.

Killinarden: includes 125 social homes and 372 affordable purchase homes - section 183 disposal approved at September 2021 Council meeting and initial planning submission made to An Bord Pleanála in October 2021.  Works will commence in late 2022 subject to planning approval.

Clonburris: will include appoximately 380 homes in phases 1 & 2 in a mix of social, affordable purchasee and cost rental tenures.  Site investigation surveys have been severely delayed but it is intended to advertise Part 8 proposals for both phases in the coming weeks.

Belgard Square North: comprising 133 cost rental homes.  Phase one of tender to select shortlisted potential contractors is complete and final tender to issue.

Rathcoole: site being reassessed with an updated report to be brought to the Elected Members before the year end.