To call on the Chief Executive to account for the delay in completing outstanding footpath repairs from the 2020 Footpath Repairs Programme, given the commitment to have that work completed by August 2021, and to provide an update on the 2021 repair programme. See response to previous question below. https://membersnet.southdublin.ie/Meetings/ViewDocument/71214
REPORT:
The following is a progress update on 2021 Path Repairs in the Lucan Area
Ardeevin Estate- Tender being prepared- To Start 29/9/2021
Beech Park- Tender being prepared- To start on 4/10/2021
Chapel Hill- Tender being prepared- Complete
Cherbury Park- Works are currently taking place onsite
Esker Lawns- Works are currently taking place onsite
Hillcrest Estate- Phase 2 of the works to start on 11/10/2021
Lucan Heights- Complete
Lucan Road- Complete
Sarsfield Park- Complete
Woodview Heights- To start on 5/10/2021
The following is a progress update on Path Repairs in the Palmerstown-Fonthill Area
Culmore Road- Complete
Greenfort Estate- Complete
Hermitage Crescent- Started
Kennelsfort Rd upper-To start on 12/10/2021
Neilstown Road- Complete
St Ronans Drive- Complete
The Coppice / Dingle- Works are currently taking place onsite
The Oval- Complete
Turret Road- To Start 11/10/2021
Wood Avens- Complete
2020 Path Repairs further works by SDCC Direct Labour Crews
Larkfield Estate Works started by DL Crew, not completed yet other works took priority,works to recommence on site in next few weeks
Liffey Terrace Works started by DL Crew, not completed yet other works took priority, works to recommence on site in next few weeks
Ballyowen Lane Works started by DL Crew, not completed yet other works took priority, works to recommence on site in next few weeks