For the members of this committee we ask the Chief Executive that a report is given in regards to the future plans for the managing of the new lucan leisure campus. This is to ensure early discussions on what is needed by the community and what the council needs to implemented to ensure its management in way that gives viability but most importantly that the building of this new facility was pushed by those in the community.

REPLY: 

Lucan Swimming Pool, with a total project cost of approximately €12.9million, is currently under construction with a projected completion date of late Q1/Q2 2022.  The original construction timetable has been severely affected by site shutdowns, restarts and restrictions related to Covid-19 health and safety measures.

Separately, the existing adjacent Lucan Leisure Centre has closed for urgent structural repairs and some refurbishment works with a budget for these works of €400k included in the Council’s Capital Programme.

it is not intended that the Council will operate the facilities directly - both facilities will be under combined management after an upcoming tender process to manage, operate and maintain the facilities.  This tender will highlight the importance of local involvement and access to the facilities and provision will be made to ensure that local sporting and leisure organisations, including leisure centre users at the time of closure, and also Esker Boxing Club, whose longstanding needs for facilities are recognised by the Council. will be prioritised for use of the new facilities.